Timeline

Leased line implementation

project plan

01

Contract

• Completing data reconciliars
(financial and technical)

• Signing the contract
• Estimated completion date: 60 days after contract signature and technical approval

02 C

Preparation  –  Co-Provider
• Gathering information for site inspection (office floor plan, technical data reconciliation)
• Arranging an appointment for the site inspection
• Site inspection

03 C

Planning  –  Co-Provider
• Preparing the plan
• Plan approval with office building and building owner

04 C

Adatkapcsolat Szolgáltatás Data Connection Service
Implementation  –  Co-Provider
• Arranging appointment
• Installation execution
• Configuration
• Sending technical parameters, transferring services to Rendszerinformatika

02 R

Preparation  –
RI_logo_icon
• Gathering information for site inspection (office floor plan, technical data reconciliation)
• Arranging an appointment for the site inspection
• Site inspection

03 R

Planning  –
RI_logo_icon
• Preparing the plan
• Plan approval with office building and building owner

04 R

Implementation  –
RI_logo_icon
• Arranging appointment
• Installation execution
• Configuration
• Transfer of technical parameters necessary for using the service
• Signing of Service Transfer and Acceptance documents (report, delivery note)

• Invoicing

Please select the subject of your enquiry from the drop-down list!
Both consents are required before we can contact you about your enquiry!
Notice: Our services are only available to companies

Érdeklődésének tárgyát kérjük válassza ki a lenyitható listából!

( * kötelező mező )
Mindkét hozzájárulás szükséges, hogy felvehessük a kapcsolatot a megkeresés kapcsán!

– Szolgáltatásaink csak cégek és gazdasági társaságok számára elérhetőek –