Timeline
Co-location implementation
project plan

01
Contract
• Filling out the financial data reconciliation form
• Signing the contract
• Estimated completion date: 60 days after contract signature and technical approval
02
Preparation
• Installation of rack cabinet
• Power supply installation
• Building network connections
• Filling the access reconciliation form

03
Implementation
• Scheduling appointment for personal handover
• Handover in datacenter
• Signing of Technical and Powermeter handover documents
• Invoicing
• Occupation of cabinets